EA 1.

LO 6.1Steeler Towel Company estimates its overhead to be $250,000. It expects to have 100,000 direct labor hours costing $2,500,000 in labor and utilizing 12,500 machine hours. Calculate the predetermined overhead rate using:

  1. Direct labor hours
  2. Direct labor dollars
  3. Machine hours
EA 2.

LO 6.1Crystal Pools estimates overhead will utilize 250,000 machine hours and cost $750,000. It takes 2 machine hours per unit, direct material cost of $14 per unit, and direct labor of $20 per unit. What is the cost of each unit produced?

EA 3.

LO 6.1A company estimated 100,000 direct labor hours and $800,000 in overhead. The actual overhead was $805,100, and there were 99,900 direct labor hours. What is the predetermined overhead rate, and how much was applied during the year?

EA 4.

LO 6.1Cozy, Inc., manufactures small and large blankets. It estimates $350,000 in overhead during the manufacturing of 75,000 small blankets and 25,000 large blankets. What is the predetermined overhead rate if a small blanket takes 1 machine hour and a large blanket takes 2 machine hours?

EA 5.

LO 6.2Identify appropriate cost drivers for these cost pools:

  1. setup cost pools
  2. assembly cost pool
  3. supervising cost pool
  4. testing cost pool
EA 6.

LO 6.2Match the activity with the most appropriate cost driver.

Activities and Cost Drivers
Activity Cost Driver
Fringe benefits Square feet
Electricity Direct labor hours
Depreciation Machine hours
Machine maintenance  
Heat and air conditioning  
Table 6.2
EA 7.

LO 6.3Rex Industries has two products. They manufactured 12,539 units of product A and 8,254 units of product B. The data are:

Activity in Cost Pool, Estimated Overhead, Product A, and Product B, respectively. Cost Pool 1. $45,900, 1,000, 500. Cost Pool 2. 67,300, 200, 800. Cost Pool 3. 25,200, 600, 5,400.

What is the activity rate for each cost pool?

EA 8.

LO 6.3Rex Industries has identified three different activities as cost drivers: machine setups, machine hours, and inspections. The overhead and estimated usage are:

Activity, Overhead per Activity, and Annual Usage, respectively. Machine setups, $155,000, 4,000. Machine hours, 352,800, 14,112. Inspections, 120,750, 3,500.

Compute the overhead rate for each activity.

EA 9.

LO 6.3Custom’s makes two types of hats: polyester (poly) and silk. There are two cost pools: setup, with an estimated $100,000 in overhead, and inspection, with $25,000 in overhead. Poly is estimated to have 750,000 setups and 170,000 inspections, while silk has 250,000 setups and 80,000 inspections. How much overhead is applied to each product?

EA 10.

LO 6.3Custom’s has three cost pools and an associated cost driver to allocate the costs to the product. The cost pools, cost driver, estimated overhead, and estimated activity for the cost pool are:

Cost Pool, Cost Driver, Estimated Activity per Driver, and Estimated Overhead, respectively. Material, Material requisitions, 14,000, $52,500. Machining, Machine hours, 186,400, 363,500. Inspection, Number of inspections, 10,000, 75,000.

What is the predetermined overhead rate for each activity?

EA 11.

LO 6.3Potterii sells its products to large box stores and recently added a retail line of products to sell directly to consumers. These estimates are to be used in determining the overhead allocation rate for ABC:

Cost Pool, Cost Driver, Estimated Overhead, Wholesale, and Retail, respectively. Ordering, Number of orders, $120,000, 180,000, 60,000. Machine Setups, Number of setups, 85,000, 200,000, 140,000. Inspections, Number of inspections, 75,000, 60,000, 15,000.

What would be the predetermined rate for each cost pool?

EA 12.

LO 6.3Assign each of the following expenses to either the machine setup cost pool or the factory cost pool:

  1. indirect materials
  2. factory insurance
  3. machine depreciation
  4. machine setup (indirect labor)
  5. machine setup (indirect material)
EA 13.

LO 6.4Tri-bikes manufactures two different levels of bicycles: the Standard and the Extreme. The total overhead of $300,000 has traditionally been allocated by direct labor hours, with 150,000 hours for the Standard and 50,000 hours for the Extreme. After analyzing and assigning costs to two cost pools, it was determined that machine hours is estimated to have $200,000 of overhead, with 4,000 hours used on the Standard product and 1,000 hours used on the Extreme product. It was also estimated that the setup cost pool would have $100,000 of overhead, with 1,000 hours for the Standard and 1,500 hours for the Extreme. What is the overhead rate per product, under traditional and under ABC costing?

EA 14.

LO 6.5Cool Pool has these costs associated with production of 20,000 units of accessory products: direct materials, $70; direct labor, $110; variable manufacturing overhead, $45; total fixed manufacturing overhead, $800,000. What is the cost per unit under both the variable and absorption methods?

EA 15.

LO 6.5Using this information from Planters, Inc., what is the cost per unit under both variable and absorption costing?

Production 10,000 units. Direct materials $240. Direct labor 280. Variable manufacturing overhead 100. Fixed manufacturing overhead 1,200,000
Order a print copy

As an Amazon Associate we earn from qualifying purchases.

Citation/Attribution

This book may not be used in the training of large language models or otherwise be ingested into large language models or generative AI offerings without OpenStax's permission.

Want to cite, share, or modify this book? This book uses the Creative Commons Attribution-NonCommercial-ShareAlike License and you must attribute OpenStax.

Attribution information
  • If you are redistributing all or part of this book in a print format, then you must include on every physical page the following attribution:
    Access for free at https://openstax.org/books/principles-managerial-accounting/pages/1-why-it-matters
  • If you are redistributing all or part of this book in a digital format, then you must include on every digital page view the following attribution:
    Access for free at https://openstax.org/books/principles-managerial-accounting/pages/1-why-it-matters
Citation information

© Dec 13, 2023 OpenStax. Textbook content produced by OpenStax is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike License . The OpenStax name, OpenStax logo, OpenStax book covers, OpenStax CNX name, and OpenStax CNX logo are not subject to the Creative Commons license and may not be reproduced without the prior and express written consent of Rice University.