10.6 Evaluate and Determine How to Make Decisions When Resources Are Constrained

Principles of Accounting, Volume 2: Managerial Accounting10.6 Evaluate and Determine How to Make Decisions When Resources Are Constrained

Menu
Table of contents
  1. Preface
  2. 1 Accounting as a Tool for Managers
    1. Why It Matters
    2. 1.1 Define Managerial Accounting and Identify the Three Primary Responsibilities of Management
    3. 1.2 Distinguish between Financial and Managerial Accounting
    4. 1.3 Explain the Primary Roles and Skills Required of Managerial Accountants
    5. 1.4 Describe the Role of the Institute of Management Accountants and the Use of Ethical Standards
    6. 1.5 Describe Trends in Today’s Business Environment and Analyze Their Impact on Accounting
    7. Key Terms
    8. Summary
    9. Multiple Choice
    10. Questions
    11. Exercise Set A
    12. Exercise Set B
    13. Thought Provokers
  3. 2 Building Blocks of Managerial Accounting
    1. Why It Matters
    2. 2.1 Distinguish between Merchandising, Manufacturing, and Service Organizations
    3. 2.2 Identify and Apply Basic Cost Behavior Patterns
    4. 2.3 Estimate a Variable and Fixed Cost Equation and Predict Future Costs
    5. Key Terms
    6. Summary
    7. Multiple Choice
    8. Questions
    9. Exercise Set A
    10. Exercise Set B
    11. Problem Set A
    12. Problem Set B
    13. Thought Provokers
  4. 3 Cost-Volume-Profit Analysis
    1. Why It Matters
    2. 3.1 Explain Contribution Margin and Calculate Contribution Margin per Unit, Contribution Margin Ratio, and Total Contribution Margin
    3. 3.2 Calculate a Break-Even Point in Units and Dollars
    4. 3.3 Perform Break-Even Sensitivity Analysis for a Single Product Under Changing Business Situations
    5. 3.4 Perform Break-Even Sensitivity Analysis for a Multi-Product Environment Under Changing Business Situations
    6. 3.5 Calculate and Interpret a Company’s Margin of Safety and Operating Leverage
    7. Key Terms
    8. Summary
    9. Multiple Choice
    10. Questions
    11. Exercise Set A
    12. Exercise Set B
    13. Problem Set A
    14. Problem Set B
    15. Thought Provokers
  5. 4 Job Order Costing
    1. Why It Matters
    2. 4.1 Distinguish between Job Order Costing and Process Costing
    3. 4.2 Describe and Identify the Three Major Components of Product Costs under Job Order Costing
    4. 4.3 Use the Job Order Costing Method to Trace the Flow of Product Costs through the Inventory Accounts
    5. 4.4 Compute a Predetermined Overhead Rate and Apply Overhead to Production
    6. 4.5 Compute the Cost of a Job Using Job Order Costing
    7. 4.6 Determine and Dispose of Underapplied or Overapplied Overhead
    8. 4.7 Prepare Journal Entries for a Job Order Cost System
    9. 4.8 Explain How a Job Order Cost System Applies to a Nonmanufacturing Environment
    10. Key Terms
    11. Summary
    12. Multiple Choice
    13. Questions
    14. Exercise Set A
    15. Exercise Set B
    16. Problem Set A
    17. Problem Set B
    18. Thought Provokers
  6. 5 Process Costing
    1. Why It Matters
    2. 5.1 Compare and Contrast Job Order Costing and Process Costing
    3. 5.2 Explain and Identify Conversion Costs
    4. 5.3 Explain and Compute Equivalent Units and Total Cost of Production in an Initial Processing Stage
    5. 5.4 Explain and Compute Equivalent Units and Total Cost of Production in a Subsequent Processing Stage
    6. 5.5 Prepare Journal Entries for a Process Costing System
    7. Key Terms
    8. Summary
    9. Multiple Choice
    10. Questions
    11. Exercise Set A
    12. Exercise Set B
    13. Problem Set A
    14. Problem Set B
    15. Thought Provokers
  7. 6 Activity-Based, Variable, and Absorption Costing
    1. Why It Matters
    2. 6.1 Calculate Predetermined Overhead and Total Cost under the Traditional Allocation Method
    3. 6.2 Describe and Identify Cost Drivers
    4. 6.3 Calculate Activity-Based Product Costs
    5. 6.4 Compare and Contrast Traditional and Activity-Based Costing Systems
    6. 6.5 Compare and Contrast Variable and Absorption Costing
    7. Key Terms
    8. Summary
    9. Multiple Choice
    10. Questions
    11. Exercise Set A
    12. Exercise Set B
    13. Problem Set A
    14. Problem Set B
    15. Thought Provokers
  8. 7 Budgeting
    1. Why It Matters
    2. 7.1 Describe How and Why Managers Use Budgets
    3. 7.2 Prepare Operating Budgets
    4. 7.3 Prepare Financial Budgets
    5. 7.4 Prepare Flexible Budgets
    6. 7.5 Explain How Budgets Are Used to Evaluate Goals
    7. Key Terms
    8. Summary
    9. Multiple Choice
    10. Questions
    11. Exercise Set A
    12. Exercise Set B
    13. Problem Set A
    14. Problem Set B
    15. Thought Provokers
  9. 8 Standard Costs and Variances
    1. Why It Matters
    2. 8.1 Explain How and Why a Standard Cost Is Developed
    3. 8.2 Compute and Evaluate Materials Variances
    4. 8.3 Compute and Evaluate Labor Variances
    5. 8.4 Compute and Evaluate Overhead Variances
    6. 8.5 Describe How Companies Use Variance Analysis
    7. Key Terms
    8. Summary
    9. Multiple Choice
    10. Questions
    11. Exercise Set A
    12. Exercise Set B
    13. Problem Set A
    14. Problem Set B
    15. Thought Provokers
  10. 9 Responsibility Accounting and Decentralization
    1. Why It Matters
    2. 9.1 Differentiate between Centralized and Decentralized Management
    3. 9.2 Describe How Decision-Making Differs between Centralized and Decentralized Environments
    4. 9.3 Describe the Types of Responsibility Centers
    5. 9.4 Describe the Effects of Various Decisions on Performance Evaluation of Responsibility Centers
    6. Key Terms
    7. Summary
    8. Multiple Choice
    9. Questions
    10. Exercise Set A
    11. Exercise Set B
    12. Problem Set A
    13. Problem Set B
    14. Thought Provokers
  11. 10 Short-Term Decision Making
    1. Why It Matters
    2. 10.1 Identify Relevant Information for Decision-Making
    3. 10.2 Evaluate and Determine Whether to Accept or Reject a Special Order
    4. 10.3 Evaluate and Determine Whether to Make or Buy a Component
    5. 10.4 Evaluate and Determine Whether to Keep or Discontinue a Segment or Product
    6. 10.5 Evaluate and Determine Whether to Sell or Process Further
    7. 10.6 Evaluate and Determine How to Make Decisions When Resources Are Constrained
    8. Key Terms
    9. Summary
    10. Multiple Choice
    11. Questions
    12. Exercise Set A
    13. Exercise Set B
    14. Problem Set A
    15. Problem Set B
    16. Thought Provokers
  12. 11 Capital Budgeting Decisions
    1. Why It Matters
    2. 11.1 Describe Capital Investment Decisions and How They Are Applied
    3. 11.2 Evaluate the Payback and Accounting Rate of Return in Capital Investment Decisions
    4. 11.3 Explain the Time Value of Money and Calculate Present and Future Values of Lump Sums and Annuities
    5. 11.4 Use Discounted Cash Flow Models to Make Capital Investment Decisions
    6. 11.5 Compare and Contrast Non-Time Value-Based Methods and Time Value-Based Methods in Capital Investment Decisions
    7. Key Terms
    8. Summary
    9. Multiple Choice
    10. Questions
    11. Exercise Set A
    12. Exercise Set B
    13. Problem Set A
    14. Problem Set B
    15. Thought Provokers
  13. 12 Balanced Scorecard and Other Performance Measures
    1. Why It Matters
    2. 12.1 Explain the Importance of Performance Measurement
    3. 12.2 Identify the Characteristics of an Effective Performance Measure
    4. 12.3 Evaluate an Operating Segment or a Project Using Return on Investment, Residual Income, and Economic Value Added
    5. 12.4 Describe the Balanced Scorecard and Explain How It Is Used
    6. Key Terms
    7. Summary
    8. Multiple Choice
    9. Questions
    10. Exercise Set A
    11. Exercise Set B
    12. Problem Set A
    13. Problem Set B
    14. Thought Provokers
  14. 13 Sustainability Reporting
    1. Why It Matters
    2. 13.1 Describe Sustainability and the Way It Creates Business Value
    3. 13.2 Identify User Needs for Information
    4. 13.3 Discuss Examples of Major Sustainability Initiatives
    5. 13.4 Future Issues in Sustainability
    6. Key Terms
    7. Summary
    8. Multiple Choice
    9. Questions
    10. Thought Provokers
  15. A | Financial Statement Analysis
  16. B | Time Value of Money
  17. C | Suggested Resources
  18. Answer Key
    1. Chapter 1
    2. Chapter 2
    3. Chapter 3
    4. Chapter 4
    5. Chapter 5
    6. Chapter 6
    7. Chapter 7
    8. Chapter 8
    9. Chapter 9
    10. Chapter 10
    11. Chapter 11
    12. Chapter 12
    13. Chapter 13
  19. Index

Companies use various resources to be productive. These resources, which include time, labor, space, and machines, are limited, thus constraining the ability of a company to have unlimited productive capacity. For example, a retail store is constrained by the amount of floor space available to display its goods, while a law office may be constrained by the number of hours the paralegal team can feasibly work. These constraints require companies to make decisions on the best ways to allocate their resources in a way that maximizes the benefit to the firm. This situation is especially true when a company is operating at capacity or makes multiple products or provides multiple services.

The question as to which products and how many should be made is a common constraint problem. For example, consider a business that runs at capacity, making four products by running two eight-hour shifts per day, seven days a week for 50 weeks per year. This business is limited to 5,600 working hours per year (8 hr. shifts × 2 shifts × 7 days per week × 50 weeks) unless a third shift is added. Adding a third shift may be prohibitive for any number of reasons, including local ordinances that prevent operating twenty-four hours a day, Environmental Protection Agency constraints, or the down-time of the machines that is required several hours a day for maintenance and calibration. What is the best way for this company to use these work hours? Which products should it produce first and how many of each should it produce?

These types of situations constrain, or limit, management’s ability to use their facilities and workforce. Having limited availability of a resource, such as time, labor, or machine hours means that item becomes a scarce resource. A constraint is a scarce resource that limits the output or productive capacity of the organization.

Ordinarily, there are very few actual constraints in any process. Sometimes, there is only one. However, the existence of a constraint can have a major effect on the productivity of an organization. This fact applies to all types of entities, such as production facilities or service providers. One way to view this issue is to consider the old cliché that a chain is only as strong as its weakest link. In the example, when trying to measure or estimate an organization’s maximum efficiency, its results will often be reduced by the overall negative effects of the constraints. When the constraint slows production, it is called a bottleneck. Managers are often faced with the problem of deciding how to best use a scarce resource to prevent bottlenecks. Under the constraint of limited resources, how do managers make decisions when they are working within these conditions?

Fundamentals of How to Make Decisions When Resources are Constrained

As with other short-term decisions, a company must consider the relevant costs and revenues when making decisions when resources are constrained. Whether the organization facing a constraint is a merchandising, manufacturing, or service organization, the initial step in allocating scarce or constrained resources is to determine the unit contribution margin, which is the selling price per unit minus the variable cost per unit, for each product or service. The company should produce or provide the products or services that generate the highest contribution margin first, followed by those with the second highest, and so forth. The total contribution margin will be maximized by promoting those products or accepting those orders with the highest contribution margin in relation to the scarce resource. In other words, products or services should be ranked based on their unit contribution margin per production restraint, which is the unit contribution margin divided by the production restraint.

If constraints are not managed, a bottleneck usually results, meaning that production slows and a back-up occurs at stages prior to the bottleneck. For example, in producing boxes of cereal, if the cereal is produced at a rate of 1,000 ounces per minute but the bagging machines can only bag 800 ounces per minute, this will create a bottleneck. Similarly, if on a Saturday morning before a home football game, the local grocery store has ten checkout lines but only opens four of them, long lines will result from the constraint of too few checkout lanes available. Management must decide how many scarce resources (employees, in this example) to pull from stocking the shelves to running cash registers. It may be difficult to see how bottlenecks affect profitability, and they appear to be more of a timing or throughput issue. But bottlenecks can affect profitability in a number of ways. Bottlenecks at the grocery story can result in customers leaving to store shop elsewhere or can negatively affect the reputation of the store, which can impact future sales. In the cereal example, bottlenecks in the packaging area can slow the delivery of boxes of cereal to distributors and individual stores. Poor or inconsistent delivery may drive customers to purchase from other cereal manufacturers, which would have a definite impact on profitability.

A common problem relating to constraints occurs in multi-product production environments. Management will need to evaluate the constraints to determine the best mix of products that will minimize the effects of the constraints. In addition to making sure that the best product mix is chosen, managers should seek ways to increase the effective capacity of the constraint. Conceptually, there are two ways a company can do this: increase the rate of output at the bottleneck, or increase the time available at the bottleneck. Increasing the capacity of the constraint or bottleneck is also called relaxing the constraint or elevating the constraint. Some specific examples of ways to relax the constraint include:

  • Keep the production facilities open longer hours. This may allow the work-flow through the bottleneck area to be slowed and thus prevent the bottleneck from occurring. However, this may require paying workers overtime pay.
  • If working extra hours is not a viable option, then moving additional workers to the bottleneck area may be beneficial as long as the areas from which they were moved are adequately covered and additional problem areas do not result.
  • Instead of using current workers, additional staff may be hired to smooth the work flow through the bottleneck area.
  • Outsource some or all of the work in the area of the bottleneck. It may be cheaper and more cost effective to buy parts of components than to slow production due to the bottleneck.
  • Redesign the production process to prevent the bottleneck by adding more resources to eliminate the bottleneck, reorganizing the process to distribute the bottleneck-causing activities to different parts of the production process, or managing processing times at other stages prior to the bottleneck to help prevent the bottleneck form occurring.
  • Insuring a minimal number of defects and rework, since they typically slow the production process and thus add to the bottleneck.

Preventing and minimizing bottlenecks can have significant benefits to the bottom line of the company. The reduction of bottlenecks allows the company to move more products through the production phase and thus be ready to sell.

Ethical Considerations

When to Include a Lifesaving Option: The Case of the Ford Pinto

The case of the fiery Ford Pinto demonstrates that more than cost and revenue should be considered when making an ethical business decision. In the early 1970s, the Ford Motor Company set out to build a Pinto for less than $2,000. Cars were much less expensive then, and Ford had to determine whether or not to include a component part that cost around $10. Given the high cost, Ford decided not to include the component, a rubber bladder for the gas tank. However, in rear-end collisions at over 21 miles per hour, the rubber bladder component functions to prevent the gas tank from flooding the interior of the car with gasoline and gas fumes. Because of the decision not to include the component, a number of Pintos involved in collisions exploded into flames, injuring and sometimes killing the occupants.

Although Ford was aware of the defect, the company’s cost/benefit analysis indicated it was less expensive to build Pintos without the rubber bladder, even when including expected reimbursement costs for anyone injured or killed. However, the decision to allow a defective product to be built in order to reduce overall costs caused a significant hit to Ford’s reputation. Ultimately, the litigation costs for knowingly constructing a defective car were higher than the original cost of including the rubber bladder component. While Ford’s decision seemed profitable in the short-term, their financial analysis could have been improved if it also took into account long-term impacts.

Sample Data

Wood World, Inc., produces wooden desks, chairs, and bookcases. These items are produced using the same machines, and there is a maximum of 80,000 machine-hours available during the year. The information about the production time and costs for these three items is:

Variable, Desk, Chair, and Bookcase, respectively: Hours to produce 1, 0.5, 0.25. Selling price $350, $200, $175. Direct materials $40, $30, $35. Direct labor $70, $65, $50. Variable overhead $55, $50, $45. Fixed overhead $28, $32, $24.

Wood World is limited in producing its products by the number of possible machine-hours. Orders have been received for 60,000 desks, 48,000 chairs, and 40,000 bookcases, which will require 94,000 machine-hours to produce. Since there are not enough machine-hours available to fill all of the orders, which orders should Wood World fill first?

Calculations Using Sample Data

To address this question, Wood World must find the contribution margin per machine-hour since machine-hours are the constraining factor for production.

Variable, Desk, Chair, and Bookcase, respectively: Selling price $350, $200, $175 less Direct materials $40, $30, $35 less Direct labor $70, $65, $50 less Variable overhead $55, $50, $45 equals Contribution margin $185, $55, $48 divided by Hours to produce 1, 0.5, 0.25 equals Contribution margin per machine hour $185, $110, $192.

Final Analysis of the Decisions

Wood World should fulfill the orders for bookcases first, desks second, and chairs last. The bookcases provide the highest contribution margin per machine-hour, followed by desks and then chairs. Maximizing the contribution margin per constraint, in this case per machine-hour, is the best way for Wood World to manage the constraint. How many of each item will be produced?

Available machine hours 80,000 plus Hours to fill bookcase orders (40,000 times 0.25) 10,000 equals Remaining hours 70,000. Remaining hours plus Hours to fill desk orders (60,000 times 1) 60,000 equals Remaining hours 10,000. Remaining hours divided by Hours needed to produce chairs 0.50 equals Chair orders that would need to be filled 20,000.

Therefore, based on contribution margin and the constraint of machine hours, Wood World should fill all 40,000 of the bookcase orders first, then fill the 60,000 desk orders and, and fill 20,000 of the chair orders last.

Are there any qualitative issues that Wood World should consider? One concern may be that customers who typically buy a desk and chair together may not be able to do so if the chair production is affected by a bottleneck. Another qualitative issue in keeping with the furniture example is that a company might find producing dining room tables to be significantly more profitable than matching chairs or matching cupboards. However, they will still be required to produce the less profitable chairs and cupboards, because many consumers will want to buy all three items as a set.

The benefits of effectively managing constraints can be enormous. Managers need to understand the positive impact effective management of constrained resources can have on the company’s bottom line. The contribution margin per unit of the scarce resource can be used to assess the value of relaxing the constraint. When there is unsatisfied demand for a single product because of a constraint, the value of additional time on the constraint is simply the contribution margin per unit of the scarce resource for that product. When there are two or more products with unsatisfied demand, the value of additional time on the bottleneck would be the largest contribution margin per unit of the scarce resource for any product whose demand is unsatisfied. In many situations, when dealing with conflicting time constraints an evaluation of multiple bottlenecks might identify a viable solution. While many bottleneck issues and their solutions could be somewhat complex, others might be addressed more simply. For example, in some cases the problem might be solved by the addition of an additional work shift.

Concepts In Practice

Distributing Caseloads at a Law Firm

As a new business school graduate, you landed you first job in the human resources department of large national law firm in New York City. Your position is providing you with many opportunities to learn about the company and the various tasks for which the human resources department is responsible. Your most recent assignment is to determine the best way to distribute caseloads to the junior level attorneys based on their areas of expertise and to assign paralegal hours to assist the junior level attorneys. What are the constraints with which you are dealing? What information do you need to properly complete this assignment? What type of analysis would be required to effectively allocate caseload hours?

Order a print copy

As an Amazon Associate we earn from qualifying purchases.

Citation/Attribution

Want to cite, share, or modify this book? This book uses the Creative Commons Attribution-NonCommercial-ShareAlike License and you must attribute OpenStax.

Attribution information
  • If you are redistributing all or part of this book in a print format, then you must include on every physical page the following attribution:
    Access for free at https://openstax.org/books/principles-managerial-accounting/pages/1-why-it-matters
  • If you are redistributing all or part of this book in a digital format, then you must include on every digital page view the following attribution:
    Access for free at https://openstax.org/books/principles-managerial-accounting/pages/1-why-it-matters
Citation information

© Dec 12, 2022 OpenStax. Textbook content produced by OpenStax is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike License . The OpenStax name, OpenStax logo, OpenStax book covers, OpenStax CNX name, and OpenStax CNX logo are not subject to the Creative Commons license and may not be reproduced without the prior and express written consent of Rice University.